Watch: Time-lapse of accelerated construction on CP rail project
Written by RT&S StaffIn late May of 2016, Canadian Pacific workers had exactly 20 hours and 5 minutes between trains to excavate and install a concrete underpass under an important section of CP Railway track.
This marked the beginning of the Mon’s Crossing Underpass Project in Whistler, British Columbia.
Watch the time-lapse video here.